Policy

Rajasthan Unveils Draft of Hybrid Wind-Solar Energy Policy, 2019

The largest state in the country, Rajasthan has come up with a draft of solar-wind hybrid policy that aims to achieve 2000 MW Wind Power capacity. The target is set for the fulfilment of Renewable Purchase Obligation (RPO) of State Discoms in respect of wind energy as determined by RERC up to 2023-24.

The National Institute of Wind Energy (NIWE) has assessed a Wind Power potential of 18770 MW in the Rajasthan.

The state will allow setting up of the projects that were already approved before 31.03.2016 (31st March 2016) by the State Level Empowered Committee under Wind Policy, 2012 for sale of power to Discoms of Rajasthan at the weighted average tariff determined through competitive bidding from the first lot of wind power project for fulfilment of Renewable Purchase Obligation (RPO) target.

Rajasthan state wants to promote Wind Power Projects with storage systems to reduce the variability of output of Wind Power into the grid and to ensure availability of firm power, therefore  5% of RPO target in MW including Solar/Wind-Solar Hybrid with Storage and will be in addition to the RPO target.

Other Highlights are:

For the already functioning wind energy projects, the state will promote Repowering of existing wind turbines of capacity below 1MW which have remained in operation for at least 10 years.

The allotment of land to the Wind Power Developers can be done as per the provisions of Rajasthan Land Revenue (Allotment of Land for setting up of Power plant based on Renewable Energy Sources) Rules, 2007 as amended from time to time.

For setting up of Wind Power Project, maximum allotable land to the Developer shall be 3 Hect. /MW. For the wind power projects with storage system, additional land will be allotted as per the rules of the Revenue Department, Govt of Rajasthan.

In the case of land allotment, submission of cash security deposit of Rs. 3 lac/ MW will be required. The state will also look into private lands for setting up wind projects.

However, No wind generation project can be set up if the land falls in the areas like National Parks and Sanctuaries, Area of Outstanding Natural Beauty (AONBs), Natural Heritage Site, sites of Archeological importance and sites of Special Scientific Interests and other important landscapes.

To read more about the draft of Rajasthan Hybrid policy, click here

I am Renew

Recent Posts

Modi Govt approved loan subsidies for 47 ethanol projects in Bihar

The central government has informed Parliament that 47 projects in Bihar have received in-principle approval…

3 days ago

Central govt urges Dairy Federations to join circular economy, biogas revolution

The Secretary for Department of Animal Husbandry & Dairying (DAHD), Alka Upadhyaya, has called on…

3 days ago

India’s ethanol blending reaches 16.9%, says Hardeep Singh Puri

Just as the quest of the nation for green energy is gaining unprecedented pace in…

3 days ago

Hithium to Supply 640MWh Energy Storage for Woolooga BESS Project

Hithium, a global energy storage product provider, announced the supply of 640 megawatt-hours (MWh) of…

4 days ago

BCL Industries to build 150 KLPD ethanol project; gets nod for 75 KLPD bio-diesel plant

BCL Industries has announced that it has received environmental clearance to set up a 150…

4 days ago

Blue Planet acquires Smart Environmental Group to strengthen its operations in New Zealand

Singapore headquartered sustainable waste management provider Blue Planet Environmental Solutions Pte. Ltd. has acquired Smart…

4 days ago