The news, even if somehow expected, was shocking when it finally came. ACME solar, the firm that had made the audacious Rs 2.44 per Kwh bid for a solar project in Rajasthan back in 2016, was cancelling the project. While that cancellation will go through the familiar legal and bureaucratic hoops now, the fact is, India’s solar boom has been stalling for a while now. Corona hit 2020 might still see small wins, like solar overtaking wind in India, but the big picture remains hazy.
While fresh capacity has been added since then, the rate of addition has certainly slowed down after hitting a peak in 2017. Ironically, the Rs 2.44 record, when it was finally broken this year in June, by Spanish major Solarpack , it hardly drew any such hopes of a coming boom. When we last checked, PPA’s for these bids were still pending, due to lack of demand. That’s just one of the reasons low prices are no longer going to cut it.
What is really interesting is how, in the past 18 months, bids in the middle east and now, Portugal, have comprehensively broken those records.
First, we had Abu Dhabi’s AI Dhafra 2GW project, promoted as the world’s largest single solar PV project where the winning bid came in at 1.35 US cents, a record at the time. Even before work had started here though, came news of a stunning bid at Portugal’s solar auctions, with the lowest bid of 0.132 cents, or 98 paise in rupee terms. So just how did these projects manage such low bids?
In Portugal, these auctions come with an interesting 15 year PPA structure, at the end of which developers can sell the power produced at merchant rates for the remaining 15 year life of the project. It is this second half of the project where calculations have been based, on getting an ‘in’ to the grid at these low prices, to presumably recoup profits in the second half of the project life cycles. That is one reason many analysts have called some of these bids ‘speculative’, although the government of Portugal is hardly complaining, as long as the projects come up.
In the Al Dhafra project, the conditions in the RFP document were really investor friendly. These included:
Speaking to a market expert for the Portugal bids, we heard this. More Precision. Bidders assumed very negligible O&M / repair costs for the 15 year PPA period to just about break even. Then, 30 year useful asset life was assumed and merchant sales for the remaining 15 years with assumed market price at between 50 to 60 euros/MWH , which seems inflated to many watchers. Thus, the real value is post PPA. IRR expectation in these are also lower at 4 to 5%, due to much cheaper financing. Finally, Portugal as a young market (like India in 2016?) and this is a volume acquisition/market share game.
On the Abu Dhabi bid, a local expert from one of the bidders points out that the Abu Dhabi procurement of solar PV projects (Dhafra IPP) – has some unique features (different from other Middle Eastern procurements).
For instance, the RFP itself stipulates a series of “time of day” and “time of year” concepts which builds in a multiplication factor on the base tariff which is publicly read out (essentially it adjusts the actual generation with the multiplication factor). The RFP also asks for BESS (Battery and Energy Storage Service) option but that is not built into the LEC.
The multiplication factors as below:
Summer Peak Summer Off-Peak Winter Peak Winter Off-Peak-10 AM to 10 PM 10 PM to 10 AM 10 AM to 10 PM 10 PM to 10 AM
Multiplication Factor 2.30 1.60 1.30 1.00
So generation is multiplied to arrive at the adjusted generation – in effect LEC is c. 1.6 times the public read out.
The other factor is that the RFP allows a hard mini perm financing – which essentially implies a refinancing risk at the maturity date. The difference in this case is that the procurer takes the risk and based on the refinancing terms adjusts the tariff – so in effect (at a high level) the LEC as publicly declared now – can change up or down based on the refinancing terms.
Add to these the certainty in terms of land availability, equipment pricing, power evacuation infrastructure, and assurance of timely payments, all issues plaguing the solar sector massively now in India, and you know that the world has moved on, at least when it comes to the best solar prices now .
AM Green has placed India's largest electrolyzer order with John Cockerill Hydrogen for one of…
By-Nipun OS India's energy goals for the next two decades are threefold: achieve energy security,…
How do you find the Indian CBG market on this visit? What’s the general sentiment?…
MIROSLAV BENKA, MD of BAUR FOLIEN talks to I am Renew and explains its business…
Biogas developer & innovator, Sistema.bio has acquired Bengaluru headquartered Inclusive Energy (IE) which is at…
ARYA, the project development division of GPS Renewables, has secured INR 100 crore in mezzanine…